SIGNATURE PAGE
I certify that I have this report
and in my opinion, it is satisfactory in scope and quality as a partial
fulfillment of the requirement for the Bachelor’s Degree in civil engineering
third year first part held at two different locations namely Baluwakhani for bridge
survey and Budhanilkantha School for topographic and road survey held from 20th
to 30th Ashwin 2074.
……………………………
Er. Bimal Bhattarai
(Camp
coordinator)
Preface
This report is the outcome of the "Survey Camp
2074" organized by Survey Instruction Committee, Department of Civil
Engineering of Kathmandu Engineering College for the students of 072 BCE Batch,
as part of the curriculum for the subject of Survey Camp prescribed by
Tribhuvan University, Institute of Engineering. The camp was held in
Budanilkantha School for a total of 10 days and entailed the practical
application of the knowledge acquired during the second year on the subject
Surveying I &II for two consecutive semesters.
The
report reflects the methodology, observations and calculations made by the
students in the Camp with the corresponding drawings. The large portion is of
course covered with elements of topographic surveying, and then those of road
alignment and bridge survey
The
survey camp promoted team work, proper handling of instruments and
responsibility of field and office work simultaneously. Also, it strengthened
our capabilities in major and minor traversing, RL transformation, detailing
and preparation of topographic map, setting out of curve, road and bridge site
survey. Moreover, it developed our confidence on the subject.
This
report is the result of hard work and dedication put forward by the students
who thrive for knowledge and new ideas. Thus we feel it deserves the tolerances
and excuses for the error or blunders present, despite the best efforts.
Group 2
Hemant
Adikhari
Krishna Kamal Sah
Nabindra
Chalise
Prawal Shrestha
Rajesh Kaji Shrestha
Acknowledgements
This report is the outcome of the survey camp 2074
conducted by the Survey Instruction committee, Kathmandu Engineering College.
Thus, we like to express our deep gratitude to the Survey Instruction
committee, Department of Civil Engineering, KEC, for organizing the survey
Camp-2074 for 2072 BCE Batch.
We have our special thanks to our teacher Er. Bimal
Bhattarai (Survey Co-ordinator) for his decent coordination which was
praiseworthy. We found all of our teacher's very hard
We would also like to thank the survey camp staffs
Mr. Ganesh Raj Basaula, Mr. Deepak Raj Upreti, Mr. Deepak Shrestha, Mr. Bhagwan
Thapa , Mr. Buddhi Ram Chaudhary for their great help during the camp.
Our heartily
thanks goes to all others seniors and individuals who helped and guided us with the experience they had, for
preparation of survey report. We would also like to thank all the staffs of
Budhanilkantha School for helping us stay at the camp site.
The camp was over with total success, and we have
found it really fruitful.
TABLE OF
CONTENTS
Signature page |
|||||||||||||
Preface |
|||||||||||||
Acknowledgement |
|||||||||||||
Salient of contents |
|||||||||||||
Camp Working Time Schedule |
|||||||||||||
Camp Working Time Schedule Detail |
|||||||||||||
SECTION –I |
|||||||||||||
|
|||||||||||||
CHAPTER 2:
TOPOGRAPHIC SURVEY |
|||||||||||||
2.1 Objective |
|||||||||||||
2.2 :brief description of the
area |
|||||||||||||
2.3 norms(Technical specification) |
|||||||||||||
2.4 Equipment |
|||||||||||||
|
|||||||||||||
2.5.1 Reconnaissance |
|||||||||||||
2.5.2Major traverse |
|||||||||||||
2.5.3 minor traverse |
|||||||||||||
2.5.4 levelling |
|||||||||||||
2.5.5 two peg test |
|||||||||||||
2.5.6 contouring |
|||||||||||||
2.5.7 computation and plotting |
|||||||||||||
2.6 comments and conclusion |
|||||||||||||
CHAPTER 3:
BRIDGE SITE SURVEY |
|||||||||||||
3.1 objectives |
|||||||||||||
|
|||||||||||||
3.3 hydrology and geology of soil |
|||||||||||||
3.4 technical specification |
|||||||||||||
3.5 Equipment and Accessories |
|||||||||||||
3.6
Methodology |
|||||||||||||
3.6.1 site selection |
|||||||||||||
3.6.2 topographic survey |
|||||||||||||
3.6.3 longitudinal section |
|||||||||||||
3.6.4 Cross section |
|||||||||||||
3.6.5 levelling |
|||||||||||||
3.6.6 detailing |
|||||||||||||
3.6.7 |
|||||||||||||
3.7 comments and conclusion |
|||||||||||||
CHAPTER 4: ROAD ALIGNMENT |
|||||||||||||
4.1 Brief description of the project
area |
|||||||||||||
4.2 hydrology and geology |
|||||||||||||
4.3 soil |
|||||||||||||
4.4 norms |
|||||||||||||
4.5 Equipment and accessories |
|||||||||||||
4.6
design parameters |
|||||||||||||
4.7 Methodology |
|||||||||||||
4.7.1Reconnaissance |
|||||||||||||
4.7.2 Horizontal alignment |
|||||||||||||
4.7.3 Vertical alignment |
|||||||||||||
4.7.4 Levelling |
|||||||||||||
4.7.5Longitudinal section |
|||||||||||||
4.7.6 Cross section |
|||||||||||||
4.7.7 topographic survey of road |
|||||||||||||
4.8 STRUCTURES |
|||||||||||||
4.8.1 retaining structure |
|||||||||||||
4.9 curves |
|||||||||||||
|
|||||||||||||
SECTION-II |
|||||||||||||
1.
TOPOGRAPHIC
SURVEY ·
DATA AND CALCULATION ·
MAPS AND GRAPHS |
|||||||||||||
2. ROAD ALINGMENT ·
DATA AND CALULATION ·
MAPS NAD GRAPH ·
|
|||||||||||||
3. BRIGGE SITE SURVEY ·
DATA AND CALULATION ·
MAPS NAD GRAPH |
|||||||||||||
|
SALIENT FEATURES
Name of the project: Survey Camp
2074
Description
of the project:
Location:
1. Region: Central Development Region
2.
Zone: Baghmati
3.
District:
Kathmandu
4. MUNCIPALITY : Budhanilkantha MUNCIPALITY
Latitude: |
270 46' 55.52"N |
Longitude: |
85 0 21' 34.2" E |
Site: Budhanilkantha School for
detailed survey and road survey and a Pipalbote Kholsa at
Baluwakhani, Kapan for
bridge surveying.
Geographical
features:
l. Terrain:
Hilly
2. Climate: Mild temperature
3.
Geology: Plains
and hills composed of soils and rocks
4.
Vegetation: Good
Descriptions of works:
Traversing:
1.
No. of major traverse stations :22
2.
No. of minor traverse stations: 11
3.
No. of minor loops: 1
4.
Length of perimeter:1226.032
5. Longest
leg length: 79.416m
6.
Shortest leg length:44.108m
Details of the data taken are in the
observation sheets.
Scale:
Topographic Map:1:500
Major and minor traverse:
Contour Interval: 1m
Detailing:
Area:
The minor traverse cover the LRC and Boys Hostel and football ground
Road alignment.
1. Road type: Village Road
2. Surface:
Earthen
3.
Length of road:
4.
No. of intersection points:10
5.
Cross section: 10m left and 10m right of both sides of center
line.
6.
Longitudinal section: in every 20m of the length.
Details of the data taken are in the observation sheets.
Scale:
•
Topographic
Map: I :500
•
Longitudinal
section: Horizontal=1:1000
Vertical = 1:100
•
Cross
section: Horizontal = 1:100
Vertical
= 1:100
•
Contour
interval: 1m
Bridge Site Survey:
I.
Bridge Span:
2. Cross
Section: 120m on upstream and 50m on downstream at 25m interval. Details of the
data taken are in the observation sheets.
Scale:
Topographic Map:
1:500
Longitudinal
section: Horizontal = 1:500 Vertical = 1:50
Cross section:
Horizontal : 1:100
Vertical = 1:100
Contour
interval: 1m
DATE |
Description of work |
20th
Ashwin,2074 |
Reconnaissance
and major traverse |
21th
Ashwin,2074 |
Major
traverse computation |
22th
Ashwin,2074 |
Minor traverse computation |
23th
Ashwin,2074 |
Two peg test and fly levelling |
24th
Ashwin,2074 |
Bridge site survey (racy and
horizontal angle measurement) |
25th
Ashwin,2074 |
Bridge site (detailing with
theodolite) |
26th
Ashwin,2074 |
Road alignment |
27th
Ashwin,2074 |
Detailing of road alignment |
28th
Ashwin,2074 |
Detailing of major traverse |
29th
Ashwin,2074 |
Detailing of minor traverse
and and field verification |
CAMP WORKING SCHEDULE SUMMARY
Descriptions of the work done on the respective days:
20th Ashwin
2074
We were given brief
description of the area by our teachers and guided us for reconnaissance of the
area for fixing Major control stations. The major control points were fixed
fulfilling the required norms, following the referencing. Then two-way
measurement of traverse legs was done.
21th Ashwin
2074
For the traverse
formed, horizontal and vertical circle readings were taken. Two sets of
horizontal readings were taken and one for vertical reading.
22th Ashwin
2074
Reconnaissance followed by marking and
fixing the minor stations was done enclosing the assigned area so as to achieve
maximum details. Referencing, two-way distance measurement was done. Internal
angle measurement was done by total station.
23th Ashwin
2074 Two peg test was carried out to find out collimation error in provided
auto level. Fly levelling was done form BM at Budhanilkantha Temple premises to
TBM established inside Budhanilkantha School and was checked if it was under
the precision or not. After that, the RL transfer was done from TBM to all the
major stations.
24th Ashwin
2074
We were taken to the site of Bridge Survey, Kapan,
Baluwakhani. After reconnaissance bridge axis was selected and triangulation
stations were fixed such that all stations were visible from base stations and
well-conditioned triangle was formed. The necessary angular measurement was
done by total station and base lines was measured by tape. We worked on bank
opposite to bank with TBM. Details were taken from stations on this bank.
25th Ashwin
2074
On this day, we worked on bank containing TBM. The
necessary horizontal circular and vertical readings were taken by theodolite.
Base length was measured by tape. Tachometric detailing was carried by
theodolite and staff. The left details were taken alone with deepest points
reading along cross section. The bearing of line joining stations
26th Ashwin
2074
Teachers instructed us on alignment of road and
mentioned all the norms to be achieved on the first day, Cross sections details
were taken on every 20m interval and at tangent points and mid points of the
curve.
27th Ashwin
2074
28th Ashwin
2074
The detailing of minor
traverse was carried out with the help of total station. The field verification
of the major and minor traverse was plotted in grid sheet.
29th Ashwin
2074
Remaining work of
detailing was done with the help of theodolite.
30th Ashwin
2074
Compilation of all the
data were done and checked if any data's have been missed. On completing the
field work, we returned from the survey camp.
INTRODUCTION
Surveying is an art
and science of determining the relative position of point on above or beneath
the surface of the earth surface and presentation of
this information either graphically or numerically by means of angular and linear measurements. It is the most important
subject matter before and during all engineering works like civil engineering
works such as designing and construction of highways, water supply systems, irrigation
projects, buildings etc. as
all these works require preliminary and detail designs
for which the knowledge of surveying is the essential factor to be considered.
Surveying is the
backbone or the preliminary task for the execution of any civil engineering
projects. The science of surveying has been developing since the very initial
stage of human civilization according as per requirements. The art of surveying
and preparation of maps has been practiced from the ancient times and further
the advancement till present. The objective of survey is to prepare plan or map
so that it may represent the area on
the horizontal plane. A plan or map is the horizontal projection of an area and
shows only horizontal distances of the points. Vertical distances between the
points are, however, shown by contour lines. In the absence of map, it is
impossible to layout the road alignment, canals, tunnels, transmission power
lines etc. Detailed map or topographical map of the site is essential for any
engineering project is based upon the accurate and complete survey work.
The main objectives of surveying courses allocated for civil
engineering students is to promote them the basic knowledge of different
surveying techniques relevant to civil engineering works in their professional
practice. The completion of all
surveying courses including ten days survey camp work organized by the
Department of Civil Engineering, “Survey Instruction Committee” of
Advanced College of Engineering and Management , give better enhancement to
students to use all surveying technique covered in lecture classes. It also build student’s confidence to conduct
engineering survey or necessary field works by own decision on planning and
execution of field works as per the required accuracy by using allocated
instruments and in allocated schedule.
The B.E. third year students of
2072 batch comprising 121 students; were on 10 days survey camp dated from 20th
Ashwin to 30th Ashwin of 2074 in Budhanilkantha,school, budhanilkantha
,Kathamndu, Nepal organized by
the Survey Instruction committee, Kathmandu College. The survey camp was taken
as a part of course of 4-year Civil engineering course. It gives an aid to
fulfill the main objective of surveying i.e. to produce the best & perfect
civil engineers.
As the works to be conducted during
the field works are all team works, all the field works during the camp were
performed in-group. The camp has in fact, developed the ability to make quick
decision, planning, execution etc. of the field works in students. Overall, the
survey camp helps to give a lot of information for conducting actual
engineering survey in the field.
This is a detail report of the works, which were performed by group no.
2, having five members, during the camp period. It briefly explains the working
procedures and technique used by this group during that camp period. In
addition, it also contain observations, calculations, methods of adjustment of
error, main problem faced during work and their solution, results of all
calculations and their assessments with some comments is presented in a concise
form.
1.1 OBJECTIVES OF SURVEY CAMP
Only theoretical knowledge on
surveying is not sufficient for the students to tackle any type of problems in
the real field in effective manner. So to provide a good practical knowledge on
the field, a survey camp is designed in 3rd year 1st part
of Bachelor in civil engineering.
The main objectives of survey camp
are summarized as follows:-
·
To
become familiar with the survey problems arise during field works.
·
To
become familiar with the parts of instruments, their functions and handling the
surveying instruments for its use in surveying.
·
To
promote team working and sharing responsibilities of the same work by each
individual in their own way to complete the project work within the allocated
time.
·
To
enable students in selecting the Bridge axis with proper location, to prepare
L-section and X-section of waterway and topographical map of Bridge site.
·
To
collect the required data in the field in systematic ways, to analyze,
calculate & to plot.
·
To
compute & manipulate the observed data in the required accuracy and present
it in diagrammatic and tabular form that other engineer can understand it
easily.
·
To
make connection of theoretical knowledge with actual field condition, to solve
field problems in the best way with reasonable time, cost and accuracy.
- To
complete the given project in scheduled time and thus knows the value of
time.
- To
tackle the mistake and incomplete data from the field while in office
work.
- To
know the complete method of report preparation.
1.2 SALIENT
FEATURES OF THE PROJECT
Description
of the project
Topographic
map preparation
·
Scale: Major
traverse 1:1000
Minor traverse 1:500
·
Paper size for
plotting: A0
·
Contour
interval: 1m
Control
point establishment
·
At least 1
stations (Main control station)
Major stations: 21
Minor stations: 11
·
Two set of
horizontal angle (Major)
·
One set of
horizontal angle (Minor)
·
Two way
measurements (1:2000 accuracy)
·
Fly leveling (±25√k
mm accuracy)
·
Leg ratio
(Minimum to maximum traverse leg distance)
Major 1:2
Minor 1:3
Special
techniques of surveying
·
Detailing by
total station
Road
alignment survey
·
More than 600m
chainage
·
Plan 1:500
·
Longitudinal
section ; scale= V- 1:100 or 50 & H- 1:1000 or 500
·
Cross section:
15 m interval, scale: H=V=1:100 or 1:200
·
Left right
observation: 10m on either side
Curve
setting
·
Horizontal curve
by both linear and angular method
Bridge
site survey
·
Up-stream: At
least 150m
·
Downstream: At
least 50m
·
Number of
stations: 6
·
Scale for
topographic map: 1:500
·
Contour
interval: 1m
·
Cross section:
every 25m interval, scale: H=V= 1:100 or 200
·
L-section: V=
1:50 or 100 and H=1:500 or 1000
Leveling
Before leveling was
done, two-peg test was done and corresponding correction was made. Strictly
speaking, the leveling was done in three steps:
·
Transfer of R.L. from B.M. to
T.B.M.
·
Transfer of R.L. from T.B.M to
major station
·
Transfer of R.L. from T.B.M to
minor station
1.3 PLANNING AND
ORGANIZING SURVEY CAMP
Survey camp has been designed for us
for a large no. of objectives. For achieving such objectives, planning and
organizing phase is one of the most important phases of the survey camp. To
make the survey camp fruitful, we all students along with the teachers has
planned about camping in the respective ways:
1.3.1 Group
discussion among the students
Most of civil engineering in the
professional fields is a team work. As one of the important objective of our
survey camp is to give a professional taste towards different problem raised in
the field of civil engineering, group discussion among the students help to
fulfill the objectives. Firstly the group containing 5 members each is divided
and all the members of the group has discussed about the responsibilities for
fulfilling the given task of the group by survey instruction committee.
1.3.2 Teacher’s
supervision
Survey camp has provided a platform
to learn the practical knowledge and difficulties that has been arising in the
scheduled time. Frequent assistance and supervision of the teachers were called
out. There were sufficient teachers for guidance, assistance and supervision of
the task carried out by all the groups.
1.3.3 Time
duration of the camp
Total time duration of the camp of
the 10 days. Out of which 5 days was allocated for topographic survey, 1 day
for two peg test and fly leveling, 1 day for R.L. transfer to the major and
minor traverse stations from TBM, 1 and half day for bridge site surveying and
another 1 and half day for road alignment survey.
1.3.4 Daily
scheduling of different activities
To
perform the specified task in a well-planned manner and reduce the problem of
scarcity of equipment required for the specified task, the daily work schedule
was listed below:
1.3.5
Transportation facility at the camp
The daily scheduling of the tasks
were from 7:00 A.M. in the morning till 5:30 P.M. in the evening. The camp was
held in the premises of Budhanilkantha school, which was easily accessible
through the means of transportation.
1.2 PROJECT AREA
Budhanilkantha School,Nepal
1. 3LOCATION AND
ACCESSIBILITY
1.3.1 Location
Budhanilkantha is municipality situated in a valley
at about 1444.375m above sea level in the central Nepal.
Country: Nepal
Development
region:
Central
Zone: Bagmati
District: kathmandu
Municipality: Budhanilkantha
Muncipality
Location: budhanilkantha
school
1.5.2
Accessibility
Budhanilkantha School, often referred to as BNKS, is a public boarding
school in Nepal. It is located in Narayansthan, 8
kilometres north of Kathmandu on the foothills of Shivapuri mountain (2,732 metres).[1] It is named after the Budhanilkantha
Temple which is located nearby
1.4 TOPOGRAPHY
AND GEOLOGY
Before starting our job, we should study
about the existing position of the project area related to the natural grid
line so that we can relate our result into the natural grid.
The
latitude and longitude of budhanilkantha schoolare as follows:
Latitude:
27° 46' N
Longitude:
85° 211' E
Terrain:
Steep slope
1.5 rainfall climate and vegetation
Climate:
Mild/Sub - tropical
Temperature:
Max. 35° C in summer
Min. 10° C in winter
Rainfall:
Adequate
Geological zone:
Lesser Himalaya Zone
1.6 OTHERS
Budanilkantha, situated at the foot of Shivapuri hill, was a Village
Development Committee in Kathmandu District in the Bagmati Zone before
being incorporated into the city of Budhanilkantha (along with Chapali Bhadrakali, Mahankal, Bishnu, Chunikhel and Kapan). At the
time of the 2011
Nepal census it had a population of 15,421.[1]The whole area was sub-divided into various
parts where the almost area covers educational buildings. The main buildings
are teaching block A and B, hostel block, multipurpose building and quarters.
Along with these buildings, it has basketball court, football ground.
2.
TOPOGRAPHICAL SURVEY
2 INTRODUCTION
Topographic
surveying is the process of determining the positions, both on the plan and
elevation, of the natural and artificial features of a locality for the purpose
of delineating them by means of conventional signs upon a topographic map. By
topography the shape or the configuration of the earth’s surface can be known.
The basic purpose of the topographic map is to indicate the three dimensional
relationships for the terrain of any given area of land. Thus, on a topographic
map, the relative positions of any given points are represented both
horizontally as well as vertically.
2.1 OBJECTIVES
The
main objective of the topographic survey is to prepare the topographic map of
the given area with horizontal and vertical control at required accuracy. By
topographical survey we can determine the positions both on plan and elevation,
of the natural and artificial features of a locality for the purpose of
delineating them by means of conventional sign upon a topographic Map. Apart
from this, some of other objectives are summed-up as follows:
·
Use
and become familiar with different kinds of surveying instruments.
·
Selection
and use of appropriate methods to perform the topographic survey.
·
To
provide accurate control points for plane tabling, tacheometry and detailing.
·
To
fix the alignment of roads, bridges, canals, channels etc.
·
To
determine the relative position on or beneath the surface of the earth.
·
To
layout the position of any structural and natural objects.
·
To
prepare the relief maps this enhances its utility.
2.2 BRIEF
DESCRIPTION OF THE AREA
The school was established in 1972. The school covers about 29 hectares
(574 Ropanies) of land. It is a full boarding school for students from 5th
grade to A-Level, aged 10 to 19. The school is equipped with
three full size multi-purpose sports field, a swimming pool, assembly hall,
dining hall, sports hall, Learning Resource Center, library with Wi-Fi
internet, modern science labs and living quarters for its faculty. The students
come from all over Nepal.
Teaching Block A
i)
Boys hostels
ii)
LRC
iii)
Football
ground
iv)
Basketball
Court
These buildings and the important ground features are included
between the minor traverse provided with one link traverse and four legs of
major traverse.
2.3 NORMS
(TECHNICAL SPECIFICATION)
1)
Reconnaissance
of the area:
Reconnaissance survey of the given area should be conducted. A closed traverse (major and minor) around
the given area should be formed by establishing the traverse station. Note that
the ratio of maximum traverse leg to minimum traverse leg should not exceed
2:1for major leg and 3:1 for minor legs with accuracy of 1:2000 and 1:1000
respectively in linear measurements.
2)
Establishment of
Horizontal control and Vertical control: Horizontal and vertical controls of the
given area must be determined based upon the given horizontal datum and
vertical datum. Co-ordinate of CP is given to be (X, Y) and Z co-ordinate must
be transformed from BM by means of fly leveling.
3) Two way measurement:
Two way measurement of the traverse leg should be done by the means of total
station. Accuracy of two way measurement in case of both major and minor leg
must lie within 1:2000.
4) Measurement of Horizontal Angle:
Two sets of angle measurement must be done using total station. The difference
of the two face reading should not be more than ±180⁰+twice the least count
or circle reading. It should be noted that the difference between the mean
angles of two set reading should be within a minute.
5)
In
case of minor traverse, measure only one set of horizontal angle and the
difference of the two face reading should not be more than ±180⁰+twice
the least count or circle reading.
6) Determination of RL of traverse
stations: This must be done using fly leveling (three wires)
from the given BM (Vertical Control Station) after completion of the Two Peg
Test. Accuracy in the case of Two Peg Test should not be less than 1:10000.
Balancing of back sight and fore sight for the elimination of different types
of error including collimation error. The permissible error of fly leveling is
±25
7) Adjustment of traverse:
The theoretical sum of interior angles in a closed traverse should be equal to
(2N-4)*90⁰.
The permissible angular error or the angular misclosure for the sum of interior
angles of the traverse should be less than ±
8) Plotting of traverse:
Plotting of the traverse stations is done by co-ordinate method selecting
appropriate scale, 1:1000 for the major traverse and 1:500 for the minor
traverse.
9) Drawing the contour lines:
The contour lines are drawn with the contour interval of 1m on the map with the
help of sufficient guide points.
2.4 EQUIPMENTS
The
following equipment’s were used in the topographic survey:
i)
Total
station with accessories
ii)
Staffs
iii)
Ranging
rods
iv)
Tapes
v)
Leveling
instrument with accessories
vi)
Compass
vii)
Auto
level with tripod
viii)
Arrows,
pegs, hammer Paints /Markers and plumb bobs.
TRAVERSING
Traversing is
that type of surveying in which a number of connected survey lines form the
frame work, which is used for housing, factory sides, and determination of
perimeter of lake, setting out and detailing of many engineering works. The
main purpose of traversing is to find control points. When there is large
extend of chaining triangulation, generally traversing is used. It is the
method of control survey.
The survey consists of the measurement
of
i.
Angle
between the successive lines or bearing of each line.
ii.
The
length of each line.
The direction and the length of the
survey lines are measured with the help of angle measuring instrument, total
station. If the coordinate of first station and bearing of first line are
known, the coordinates of all successive points can be computed.
Traverse is of three types:
- Close
traverse (loop traverse)
- Open
traverse
- Link
traverse
i.
Close traverse:
If a traverse starts from a point,
runs and ends on the same starting point then such traverse is called closed traverse.
These types of traverse are run for a closed field survey. In this type of
traverse, independent check is possible and adjustment can be done very easily.
D
Fig.2.1 Closed traverse C
ii.
Open traverse:
If a
traverse starts from a point, runs and ends at the point other than starting
point is called open traverse. This type of traverse is run during the route
survey like road, railway, canal, tunnel etc. In these types of traverse the
error calculation and balancing is very difficult.
B D (Unknown point)
Fig. 2.2 Open
traverse
iii.
Link traverse:
These are
geometrically open but mathematically closed traverse. This type of traverse
starts from a known point and ends at another known point. Also in this type of
traverse the calculation and balancing of error can be done easily.
B D (known point)
Fig. 2.3 Link
traverse
MAJOR TRAVERSE
The whole
site which was to be surveyed was enclosed by the numbers of inter-connecting
survey lines forming the closed circuit or the framework joining successive
major control points is known as major traverse.
2.5 METHODOLOGY
Depending upon the instrument used in
determining the relative directions of the traverse lines, there are several
methods of traversing such as:
1.
Chain
traversing,
2.
Chain
and compass traversing,
3.
Transit
tape traversing,
4.
Plane
table traversing,
5.
Theodolite
traversing.
The methodology of surveying is based on
the principle of surveying. They are as follows:
i.
Working
from whole to a part.
ii.
Independent
check.
iii.
Consistency
of work.
iv.
Accuracy
required
The different methodologies were used in
surveying to solve the problems arise in the field. These methodologies are as
follows:
2.5.1 RECONNAISSANCE (RECCE)
The planning of work is utmost to accomplish the
work without any irregularity and difficulty in the scheduled time frame or
time bound. It also helps to complete the work in the systematic order and in
the time bound with less effort. So for better planning, detailed inspection of
the area is carried out which is known as reconnaissance survey. In other word,
Reconnaissance is the exploration or initial scouting of the survey area which
involves the visiting around the area, rough planning of the traverse stations
and their numbers according to the area and topography of the site. It is done
to get the preliminary idea of the area. During the recce, one should consider
the land type, vegetation, climate and Intervisibility of stations for the
detailed planning.
The
following points are noteworthy for the fixing of the traverse stations:
- The
adjacent stations should be clearly inter-visible and cover the whole area
with least number of stations as far as possible. The traverse station
should maintain the ratio of maximum traverse leg to minimum traverse leg
less than 2:1.
- The
steep slopes and badly broken ground should be avoided as for as possible,
which may cause inaccuracy in tapping.
- The
stations should provide minimum level surface required to set up the
tripod of the instrument.
- The
traverse line of sight should not be near the ground level to avoid the
refraction.
- If
possible well-conditioned triangles should be formed to give good
graphical intersection during plotting.
Balancing of traverse:
There are two methods of balancing of traverse: -
1.
Bowditch's
method
2.
Transit
method
I. Bowditch’s method:
In this method, the total error in the
latitude and departure is distributed in proportion to the lengths of the
sides. It is mostly used to balance a traverse where linear and angular
measurements are of equal precision. This rule says:
Correction to latitude (or departure) of any side
= (Total
error in latitude (or departure)*length of that side)
Perimeter of
traverse
ii. Transit Method:
In this method, the total error in
latitude & departure is distributed in proportion to the latitude &
departure of its side. This rule is adopted when angular measurements are
precise rather than linear measurements. This role provides correction to
latitude & departure of any side.
Correction in Latitude (or Departure) of any side
= Total error in latitude or
departure × latitude (departure) of that line
Arithmetic sum of latitude (or
departure)
CLOSING ERROR:
In the closed traverse, at the time of plotting, if
the end point of the traverse does not coincide with the starting point due to
error in the measurement or any other, then it is called closing error. In the
closed traverse, the algebraic sum of latitude (SL) and the
algebraic sum of departure (SD) must be zero. Otherwise it is said to
have closing error.
\Closing error
Balancing the traverse:
-
There
are different methods of adjusting a traverse such as Bowditch Rule, Transit
rule, Graphical Method. Among them, Bowditch rule was used to adjust the
traverse in the survey camp.
2.5.4 LEVELING
It
is a branch of survey with main objective is to
i.
Find the elevations of given points with
respect to a given or assumed datum and
ii.
Establish points at a given elevations
or at different elevations with respect to a given or assumed datum.
Leveling
deals with the providing the vertical controls to all the control stations for
the preparations of the topographic map. Two types of leveling were performed
at the site, namely direct leveling (spirit leveling) and indirect leveling
(trigonometric leveling).
1.
Direct leveling
It
is the branch of leveling in which the vertical distances with respect to a
horizontal line is determined (perpendicular to the direction of gravity). It
may be used to determine the relative difference in elevation between two
adjacent points. A level provides horizontal line of sight, i.e. a line
tangential to a level surface at the point where the instrument stands. The
difference in elevation between two points is the vertical distance between two
level lines. With a level set up at any place, the difference between the rod
readings taken on these points. By a succession of instrument stations and
related readings, the difference in elevation between widely separated points
is thus obtained.
Following are some special methods of direct
(spirit) leveling:
i.
Differential leveling
It
is the method of direct leveling the object of which is solely to determine the
difference in elevation of two points regardless of the horizontal positions of
the points with respect of each other. This type of leveling is also known as
fly leveling.
ii.
Profile leveling:
It
is the method of direct leveling the object of which is to determine the
elevations of points at measured intervals along a given line in order to obtain
a profile of the surface along that line.
iii. Cross-sectioning:
Cross-sectioning
or cross leveling is the process of taking levels on each side of main line at
right angles to that line, in order to determine a vertical cross-section of
the surface of the ground.
iv.
Reciprocal leveling:
It is the method of leveling in which the
difference in elevation between two points is accurately determined by two sets
of reciprocal observations when it is not possible to set up the level between
the two points.
Temporary adjustment of level:
The
temporary adjustment of level consists of the following steps:
1.
Setting
up the level: The operation of setting up includes
fixing the instrument on the stand and leveling the instrument approximately.
2. Leveling up:
Accurate leveling is done with the help of foot screws and with reference to
the plate level. The purpose of leveling is to make the vertical axis truly
vertical.
3.
Elimination
of Parallax: Parallax is the condition when the
image formed by the objective is not in the plane of the cross hairs. Parallax
is eliminated by focusing the eyepiece for distinct vision of the cross hair
and by focusing the objective to bring the image of the object in the plane of
cross hair. Permanent adjustment of
level.
To
check the permanent adjustment of level two-peg test method should be
performed.
B B
A C B
Figure:
- Two peg test
Method:
Two
staffs were held at A and B of known length (about 40m). First, the instrument
was setup at the middle point C and both staff readings were taken. Then the
machine was held near A and both staff readings (Top, Middle, and Bottom) were
taken again. Then computation was made as follows in order to check whether the
adjustment was required or not.
The
precision obtained was less than that of required precision of 1 in 10000.
Therefore, the permanent Adjustment was done.
There
are two methods of booking and reducing the elevation of points from the
observed staff reading.
1.
Height of Instrument method
Arithmetic Check:
∑BS-∑FS=Last R.L-First R.L
2.
Rise and Fall method
Arithmetic
Check:
∑BS-∑FS=∑Rise-∑Fall= Last R.L-First R.L
Among
the two Methods Rise and fall method is widely used. After checking the
accuracy of the level by two-peg test, fly leveling was performed the known
reduced, level from the BM (benchmark) was then transferred to the given
control point 1 (CP). The R.L. of the control point 1 was then found to be
within the permissible error of ±25Ök
mm. The R.L. of the temporary benchmark was then transferred to the control
stations of the major and minor traverse. The closing error was found within
the permissible limits. Then the linear and angular adjustments were made in
each leg. All the necessary data and calculations are presented in the
following pages in this report.
2.5.5 DETAILING
Detailing
means locating and plotting relief in a topographic map. Detailing can be done
by either plane table surveying or tachometric surveying or by EDM. Some of the
steps followed while carrying out the detail survey are summed up as follows:
·
Instrument was set at each control
points with accurate centering and leveling.
·
The vertical distance from the center of
the trunnion axis to the peg at the ground was measured as the height of the
instrument.
·
The instrument was oriented with
reference to a fixed station which is already well defined.
·
The reflector was held vertically as far
as possible both for the case detail survey.
·
Hard details were not missed as far as
possible and were indicated by numbering in the reference map for the future
reference of plotting.
After
having distance and the direction obtained from the detail survey, details were
plotted in the grid sheet while already contained the major and minor traverse
stations.
2.5.6
CONTOURING
A contour is an imaginary line, which
passes through the points of equal elevation. The surface of ground is
intersected by a level surface in a line. A contour line is a line on the map
representing a contour. It represents the elevation and is one of the ways of
representing relief. While drawing the contour lines, the characteristics of
the contours should be considered.
Methods of contouring:
There
are two ways of contouring. They are namely:
1. The Direct method
2. The Indirect method
1.The direct method:
In this direct method, the contour to be plotted is
actually traced on the ground. Only those points are surveyed which happen to
be plotted.
2.The indirect method:
In this method, some suitable guide
points are selected and surveyed, the guide points need not necessarily be on
the contours. These guide points, having been plotted, serve as the basis for
the interpolation of contours. There are some of the indirect methods of locating
the ground points:
a.
By
squares
b.By
cross-sections
c.
By
tachometric method
Contour
Interpolation:
The process of
drawing contours proportionately between the plotted ground points or in
between the plotted contours is called interpolation of the contours. Interpolation
of contours between points is done assuming that the slope of ground between
two points is uniform. It may be done by anyone of following methods:
*
Estimation
*
Arithmetic
calculation
*
Graphical
method
The
characteristics of contours are
i)
Two contours of different elevations do
not cross each other except in the case of an overhanging cliff.
ii)
Contours of different elevations do not
unite to form one contour except in the case of a vertical cliff.
iii)
Contours
drawn closer depict a steep slope and if drawn apart, represent a gentle slope.
iv)
Contours
equally spaced depict a uniform slope. When contours are parallel, equidistant
and straight, these represent an inclined plane surface.
v)
Contour
at any point is perpendicular to the line of the steepest slope at the point.
vi)
A
contour line must close itself but need not be necessarily within the limits of
the map itself.
vii)
A
set ring contours with higher values inside depict a hill whereas a set of ring
contours with lower values inside depict a pond or a depression without an
outlet.
viii)
When
contours cross a ridge or V-shaped valley, they form sharp V-shapes across
them. Contours represent a ridgeline, if the concavity of higher value contour
lies towards the next lower value contour and on the other hand, these represent
a valley if the concavity of the lower value contour, lies towards the higher
value contours.
ix)
The same contour must appear on both the
sides of a ridge or a valley.
x)
Contours do not have sharp turnings.
Taking the reading at the change point on the ground
is the indirect method of locating contours. The interpolation method is used
to draw the contour lines. Interpolation of contours is done by estimation, by
arithmetic calculations or by graphical method. The eye estimation method is
extremely rough and is used for small-scale work only. Generally, arithmetic
calculation method of interpolation is used to draw the contour line.
2.5.7
COMPUTATION AND PLOTTING
For the calculations as well as plotting, we applied
the coordinate method (latitude and departure method). In this method, two
terms latitude and departure are used for calculation. Latitude of a survey
line may be defined as its coordinate lengths measured parallel to an assumed
meridian direction. The latitude (L) of a line is positive when measured
towards north, and termed Northing and it is negative when measured towards
south, and termed Southing. The departure (D) of a line is positive when measured
towards east, and termed Easting and it is negative when measured towards
south, and termed Westing. The latitude and departures of each control station
can be calculated using the relation.
Relations,
Latitude
= L*Cos q
Departure
= L*Sinq
Where,
L = distance of the traverse legs
q
= Reduced bearing
If
a closed traverse is plotted according to the field measurements, the end of
the traverse will not coincide exactly with the starting point. Such and error
is known as closing error.
Mathematically,
Closing
error (e) = Ö{(SL)
2 + (SD)
2}
And
Direction,
tanq
= SD/SL
The
sign of SL
and SD
will thus define the quadrant in which the closing error lies. The relative
error of closure = error of Closure/ Perimeter of the traverse.
= e / p
= 1/ (p / e)
The
error (e) in a closed traverse due to bearing may be determined by comparing
the two bearings of the last line as observed at the first and last stations of
traverse. If the closed traverse, has N number of sides then,
Correction
for the first line = e/N
Correction
for the second line = 2e/N
And
similarly, correction for the last line = Ne/N = e
In
a closed traverse, by geometry, the sum of the interior angles should be equal
to (2n - 4) x 900 where n is the number of traverse sides. If the
angles are measured with the same degree of precision, the error in the sum of
the angles may be distributed equally among each angle of the traverse.
The
Bowditch's method or the Transit rule is mostly used to balance a traverse
where linear and angular measurements are of equal precision. The total error
in latitude and in the departure is distributed in proportion to the lengths of
the sides.
Mathematically,
a) Correction in departure of a side of traverse
= - (Total departure misclosure/traverse perimeter)
x length of that side
b) Correction in latitude of a side of traverse
= - (Total latitude misclosure/traverse perimeter) x
length of that side
In
order to measure the lengths of the sides of the traverse, two ways taping
(forward and backward) is done. In difficult areas where taping is not
possible, other methods like Theodolite ranging is used. The difference in
values obtained by forward and backward taping is called discrepancy. In
addition, the reciprocal of the discrepancy divided by the mean of the two
measurements is called precision. Both the discrepancy and the precision for
each traverse leg should be within the given limits.
Mathematically,
Discrepancy = | Forward length
- Backward length |
And
Linear precision = 1/ (Mean length/Discrepancy)
The
coordinates of traverse stations were calculated with respect to the given
coordinate of the station “CP” and the bearing was transferred from the
station to the major stations.
MINOR TRAVERSE
The method of forming traverse connected to the one
or more station points of major traverse, which is run around the area to be
detailed, is called Minor Traversing. All the vertical and horizontal controls
are transferred from the major traverse stations. The minor traverse station
points are so chosen that maximum details can be obtained at a point during
plane tabling or tachometric surveying.
The
following steps should be followed for minor traversing: -
·
The
minor traverse stations are fixed and marked by reconnaissance.
·
Both
forward and backward measurement of the traverse leg is done which should be
within the limit 1:1000.
·
For
included angles, only one set of reading along with tachometric readings are
taken.
·
One
set of horizontal reading was taken from each station.
·
The
angular closing error must be within L.C×Ön; where n = no.
of stations.
2.6COMMENTS AND CONCLUSIONS
Hence
the coordinates of the entire major as well as minor traverse stations were
computed and were plotted in the grid sheet in suitable scale using Auto Cad
Land Development software.
The given Topography survey camp
work was finished satisfactorily within the given span of time. The subject
survey needs practice as much as possible. For surveying, theory can only take
as the introduction but if there is practice, there will be much gain of
knowledge about the techniques of surveying. Thus, this camp helps us by
practicing the survey work to gain the much essential knowledge as far as
possible. It is better to say that it provides us a confidence to perform
survey and apply the techniques at any type of problem facing during the actual
work in the future career.
3.
BRIDGE
SITE SURVEY
INTRODUCTION
Bridge site survey includes the work to carry a
survey for the construction of the bridge to join two banks of the river and
allow continuation of the road and provide easy access for the people and the
vehicle. Bridge construction is an important aspect which plays vital role in
the development of the nation and its economy basically in the context of our
country. Surveying is required for topographical mapping, while longitudinal
section of the river and the cross-section of the upstream and downstream side
of river are essential. Also the river flow level in the different sections as
well as in different seasons should be taken into consideration before the
design process of the bridge.
3.1 OBJECTIVES
The main objective of the bridge site survey is to
obtain the preliminary knowledge on selection and planning of possible bridge
site and axis for the future construction of the bridge. The purpose of the
bridge site survey is not only to prepare plan and layout of the bridge site
but also from the engineering point of view, the purpose is to collect the
preliminary data about the site such as normal water level, high flood level,
geological features of the ground, catchments areas for planning and designing
of the bridge from the details taken from the surveying. Moreover bridge
construction is an important aspect which plays major role in the development
of transportation network. Thus, surveying is required for topographical
mapping, knowledge of longitudinal sections of the river and cross-sections at
both the upstream as well as in downstream side of the river of the
construction of the bridge. The objectives of the bridge site survey can be
summed as follows:
i.
To
find the average slope of the river and its catchments area.
- To
exercise the reciprocal leveling for RL transfer in bridge axis.
- To
perform triangulation method for measuring the bridge axis and detailing
100m upstream and 50 m downstream.
- To
prepare topographical map of the bridge site and hence prepare
longitudinal and cross-section of the river at the required upstream and
downstream of the river.
- To
accumulate the past information about the high flood level, normal flow
level, river cut direction, river shifting pattern etc.
3.2 BRIEF DESCRIPTION OF THE AREA
Bridge
site survey was conducted in one of the KAPAN BALUWA KHANI. This bridge site is
surrounding with the steep hill and cultivable land. The bridge foundation or
the bridge axis was selected such that the hard rock lies below it. The river
was narrow with less meandering.
3.4 NORMS (TECHNICAL SPECIFICATION)
Establishment of control point forming well-conditioned triangle on bridge
survey.
·
Detailing
of the area about 100m U/S and 50m D/S at every 25m interval and up to 15m on
either cross side from bridge axis is taken.
·
Traversing
is done by triangulation.
·
At
least two base lines are
measured by using tape (two way measurement).
·
Sides
are computed by using sine & cosine law.
·
Distance
and bearing from B.M. to nearest station (station A) was taken.
·
Error
in interior angles of the control point polygon is distributed equally in all
stations since it lies within the permissible error (2N-4) * 90±ÖN*L.C.
But in our case (2N-4)*90± 1’ÖN where N is the
no of stations.
·
Triangles
were adjusted applying correction.
Plotting Scales
Topographic map:
1:500
L-section:
Horizontal: 1:1000
Vertical: 1:100
Cross-section:
Horizontal: 1:200
Vertical: 1:200
Contour interval: 1 m
3.5 EQUIPMENTS
The
equipment used during bridge site survey are summed up as follows:
·
Theodolite
with tripod
·
Staffs
·
Ranging
rods
·
Auto
level with tripod
·
Measuring
tape
·
Compass
with tripod
·
Pegs
·
Arrows
·
Enamel
paint or marker
3.6
METHODOLOGY
3.6.1 SITE
SELECTION
This is the major or the vital
aspect of the site selection of the proposed bridge site. There are various
factors which directly or indirectly affects the site selection of the bridge.
They are geological condition, socio-economic and ecological aspect etc. The
foundation of the proposed bridge should be laid above very stable hard rocks
at the bed of river as far as possible for the stability and long life of the
bridge. The proposed bridge site should not affect or disturb the ecological
balance of the flora and fauna of the locality in the site. The axis of the
bridge should be laid such that the flow direction of the river at the same
time the width of the river channel should be least from economical point of
view. The free board must be taken 5m in least. The starting point of the axis
of the bridge or the starting of the bridge itself should not lie or touch the
curve portion of the road. In other words, it can be said that the axis of the
bridge should not be followed by the curve while selecting the bridge.
For the purpose of
having shorter span of the bridge, the stations were such selected that the
river flow direction was made perpendicular to the flow direction of the river.
There should not be cutting or banking of the river banks by the river water at
the proposed bridge site.
3.6.2
TRIANGULATION
Triangulation is the process of forming number of
connecting triangles so as to provide the control the points. Triangulation
involves two processes, measurement of horizontal distances of any two side of
the triangle formed on the opposite side of the frame between two control point
by tape and the measurement of all the interior angles with the help of angle
measuring instrument i.e. theodolite. All the remaining lengths of the side of
the triangle is computed with the help of any one measured length and all the
measured angle of the triangle formed. The axis length of the proposed bridge
was computed as mentioned earlier using sine law of the triangle. The computed
length of the bridge axis should not differ more than 5mm.
3.6.3
LONGITUDINAL SECTIONING
Profile levelling is the process of
determining the elevations of the points at the short measured intervals along
a fix line or alignment such as the center line of the railway, highway, canal
or sewer. The fixed line may be a single straight line or it may be composed of
a succession of straight lines or of a series of straight lines connected by
curves. It is also known as longitudinal sectioning. By means of such sections
the engineer is able to study the relationship between the existing ground
surface and the levels of the proposed construction in the direction of its
length. The profile is usually plotted on specially prepared profile paper, on
which the vertical scale is much larger than the horizontal, of costs are made.
Profile levelling, like differential levelling, requires the establishment of
turning points on which both back and fore sights is taken. In addition, any
number of intermediate sights may be taken on the points along the line from
each set up of the instrument. It is generally best to set up the instrument to
one side of the profile line to avoid too short sights on the points near the
instrument. For each set up, intermediate sights should be taken after the fore
sight on the next turning point has been taken. The position of the intermediate
points on the profile is simultaneously located by chaining along the profile
and noting their distances from the point of commencement.
For the
longitudinal section of the river, the staff readings were taken at the
interval of 25m. L – Section was carried out up to 50m downstream and 100m
upstream. While taking observations on the staffs, it was held on the bed of
the river. It must be checked whether the staff is above the stone or on the
river bed. The chainage was measured along the river flow direction by
spreading tape over the water. If possible short reaches of lengths must be
taken while measuring chainage which prevents error on the linear measurement.
3.6.4 CROSS –
SECTIONING
Cross- sections are run at right
angles to the longitudinal profile and o the either side of it for the purpose
of lateral outline of the ground surface. They provide the data for estimating
quantities of earth work and for other purposes. The cross-sections are
numbered consecutively from the commencement of the Centre line and are set out
at right angles to the main line of section with the chain and tape.
Cross-sections may be taken at each chain. The length of cross-section depends
upon the nature of the work. The longitudinal and cross-sections may be worked
together or separately as per the requirement
In the case of bridge survey,
cross-sections are taken at every 15m interval. The spot heights were taken
where the change of the slope of the ground was abrupt. Cross-sections must be
taken at normal flood level, high flood level, and river banks etc. Theodolite
was used for this purpose as tacheometer.
3.6.5 LEVELLING
§ Transferring R.L. from B.M. to control points
For the determination of the
reduced level of all the control points fly leveling must be carried out to
transfer reduced level of the nearest possible bench mark to all the control
points. The R.L. of the bench mark was given to be 1570 m which was transferred
to all the triangulation stations within given accuracy. For transferring the
reduced level to opposite bank of the river Reciprocal
Levelling was used.
Reciprocal Leveling:
Horizontal F E T Fig: Intersection izontal Line e e B B A B Horizontal
Line River Riha A Level Line of
sight Level
Line e Lie River Horizontal
Line hb hb׳ hA B ha׳ ha׳ River Horizontal
Line Horizontal Line B B A A ha ha Level
Line Level Line 1 Y1 Y2 X Y P1 P2 ht e hb hbCP River A B C14 r
Fig : Reciprocal levelling
Let
A and B be the points and observations be made with a level. For the first set
up of instrument, three wire readings on both the staff held at the point A and
B are observed and the level difference between them is calculated.
The
level difference is calculated as:
Similarly
for second set up of instrument
Taking
average of two true difference of elevation, we get
2H= [ha – (hb – e)
+ (ha׳
– e) - hb׳]
= (ha – hb) + (ha׳ -
hb́ )
H =
1/2[(ha – hb) + (ha׳-
hb΄(
True difference of elevation is equal to mean of the
two apparent differences in elevation.
3.6.6
DETAILING:
The
detailing or detail survey was carried out with the help of Theodolite. The
important or the hard details which were omitted or not taken in the
longitudinal sectioning as well as in cross sectioning were taken.
Trigonometric leveling was also performed in the case of determination of
reduced level of inaccessible point. All the detailed points were noted for the
topographical view of the bridge site.
3.6.7
COMPUTATION AND PLOTTING
In the case of triangulation,
the horizontal and the vertical control of triangulation stations were determined
and the horizontal as well as horizontal control of the other stations was
manipulated later. The level or the elevation is calculated and usual checks
were applied. Then plotting was done in appropriate scale.
Plotting
Scale:
Topographic map: 1:500
3.7
COMMENTS AND CONCLUSION
In spite of the different kinds of obstacles in the
field, the fieldwork as well as the final report was completed in time. In the
field, there had some discussion on the route of the road and also in designing
the curves, which led to good results, there was some problem. However, all the
group members were very cautious and tried their best to get error free data
and calculations. The road had to be designed on a pre-designed road, so group
members felt the restrictions during the cutting and filling and also for the
construction of different retaining structures.
4. ROAD
ALIGNMENT SURVEY
INTRODUCTION
Transportation is important aspect
of socio economic, cultural development of country and the locality since every
commodity produced whether it is a food, clothing, and industrial products or
medicine needs transport at all stages from production to distribution. Since
Nepal is mountainous poor and landlocked country airway, railway, waterway,
rope way are unable to fulfill the demand of transportation. So roadway is
major part of transportation in Nepal. Among all modes road is the only mode
which give maximum services to one and all. This mode has also the maximum
flexibility for travel with reference to route, direction, time and speed of
travel and provides door to door service. There is high road demand in Nepal at
present context.
In
this survey camp we studied about road transportation, its types and simple
method of fixing road alignments.
Road classification
Roads
in Nepal are classified as follows:
1.
National
Highways: National Highways are main roads connecting East
to West and North to South of the Nation. These serve directly the greater
portion of the longer distance travel, provide consistently higher level of
service in terms of travel speeds, and bear the inter-community mobility. These
roads shall be the main arterial routes passing through the length and breadth
of the country as a whole. They are designated by letter “H” followed by a
two-digit number.
2.
Feeder
Roads: Feeder roads are important roads of localized
nature. These serve the community's wide interest and connect District
Headquarters, Major economic centers, Tourism centers to National Highways or
other feeder roads. They are designated by letter “F” followed by 3-digit
number.
3.
District
Roads: District Roads are important roads within a
district serving areas of production and markets, and connecting with each
other or with the main highways.
4.
Urban
Roads: Urban Roads are the roads serving within the urban
municipalities.
4.1 Brief
description of project area
Road alignment was conducted in
the budhanilkntha school
The road is start from one major
station and end in another major station.
4.2 OBJECTIVES
Road Alignment Survey was done to accomplish the
following objectives:
Ø To
choose the best possible route for the road such that there were a minimum
number of Intermediate Points (I.P.) thereby decreasing the number of turns on
the road.
Ø To
design smooth horizontal curves at points where the road changed its direction,
in order to make the road comfortable for the passengers and the vehicles
traveling on it.
Ø To
design vertical alignment with appropriate gradient.
Ø To
get preliminary idea of elements of roads like horizontal curve, hair pin
bands, shoulder, camber, super elevation, right of way, setbacks, road
drainage, cross drainage etc.
Ø To
prepare L-section, X-section, plan view of roads showing their elements.
4.3 TECHNICAL SPECIFICATION
The technical specification of road construction and
design are based on ‘Nepal Road Standard – 2070’ in Nepal. However we were
bound to the norms given by survey instruction committee 2070. They are
1. Carry
out reconnaissance survey and alignment selection of a road corridor (starting
point will be IP1 and the end point will be provided) more than 600m
chainage.
2. Obligatory
points, permissible gradient, bridge site, shape of valley, geometry of tentative
horizontal and vertical curves etc. must be considered to select the best
route. Always keep in mind SESE i.e. Short, Easy, Safe, Economical.
Design
Norms/Standard
ü Permissible
gradient : 1 to 12%
ü Radius
of horizontal curve should not less than 12m.
ü Points
of commence and point of tangency should not be located within the bridge axis.
ü Two
successive curves should not be overlapped.
ü Deflection
angle less than 3o, setting out of horizontal curve is not
necessary.
3. Bearing
of starting leg is to be measured and bearing of next leg is calculated with
respect to deflection angles.
4. Cross
– sectional detail be in 15m interval (also in abrupt change point) and also in
BC, MC, EC.
5. Carry
out level along the road center line passing IPs with establishing TBMs at
certain interval; close the loop, permissible error of closure must not be
greater than ±25Ök
mm.
6. Road
formation width is 5.5 m (intermediate lane), volume of cut/fill should show in
profile. Draw longitudinal profile of center lines of road in scale H = 1:1000
or 1:500 & V = 1:100 or 1:50 and cross – section in scale of h = V = 1:100
or 1:200.
7. Also
soil type, climate and rainfall pattern must be noted.
8. Distance
between IPs must be measured by total station. Accuracy required is 1:2000.
Formation level must be shown in L – section and X – section.
4.5 EQUIPMENT’S USED
- Total
station
- Reflector
- Staffs
- Level
machine
- Compass
- Ranging
rods
- Tapes
- Pegs
- Enamel
paint and marker
4.7 METHODOLOGY
4.7.1 RECONNAISSANCE
First of all preliminary inspection called
reconnaissance was done by walking through the proposed road alignment from
where the actual alignment of the road has to be run. The planning of works was
made for the intersection points (IP) where the direction of the route has to
be changed. After having complete reconnaissance the IP were fixed. For this
the inter-visibility of the IP were kept in mind and was checked and the
gradient or simply the slope between two IPs was made between 1 to 12 %
according to NRS. At the same time, the peg with the IP no. was driven at the
suitable position on the ground with references if needed. Establishment of all
IPs in correct ways is completion of 50% of work.
4.7.2 MEASUREMENT OF LENGTH AND DEFLECTION ANGLES
The distances between the IPs were measured with the
help of total station. Both forward as well as backward measurement of the
distance was carried out. The accuracy for the linear measurement of the
distance between IPs is 1:2000 as in the case of major traverse leg
measurement.
One set of horizontal angle was measured for the
deflection angle. The face left reading was observed and the deflection angles
were calculated. As the traverse formed as open traverse, no angular correction
could be made. So as far as possible, both the linear measurement as well as
the angular measurements was observed carefully and precisely.
4.7.3 RL TRANSFER FROM BM TO IPS
To prepare the map of the given
area, it was necessary to carry out the fly leveling from given BM to the IPs
of the road alignment of the road.
·
FS distance and BS distance must be in
nearly equal distance so as to eliminate errors due to focusing, refraction and
curvature. For maintaining equal distance, eye judgment and pacing is used.
·
Three wire reading is taken. At each
attempt mean value of three wires reading should not differ by 0.001m with the
middle wire reading and was checked on the field.
·
Fly leveling was run from BM to IPs and
back to BM. For the correction we established two TBMs midway in the fly
leveling.
·
The RL of each staff station was found
from rise and fall method.
·
The permissible error was ±25Ök
mm where K is the loop distance in km.
·
Closing error within the permissible
limit was distributed to all the staff stations according to their lengths
(station to staff distance)
4.5.4 CURVE SETTING
Curves are generally used on highways and railways
where it is necessary to change the direction of the motion of the vehicle. A
curve may be circular, parabolic or spiral and is always tangential to the two
straight directions commonly known as tangents. Curves which are generally used
on highways are as follows:
·
Simple
Circular Curve
·
Transition
Curve
·
Vertical
curve
But
we only design Simple Circular Curve in this alignment.
Simple Circular Curve
R R O D C B A T1 IP T2
Δ Fig: Simple Circular Curve
- Length of
tangent:
R tan (Δ/2)
Where,
R = radius of simple circular curve
Δ = deflection angle
- Length of
long chord:
2R Sin (Δ/2)
- Apex
distance: R
(Sec(Δ/2) – 1)
- Mid
ordinate: R
(1 - Cos(Δ/2))
- Length of
curve:
ΠRΔ
180°
- Chainage of
T1: Chainage
of IP - R tan (Δ/2) …………….......BC
- Chainage of
D: Chainage
of T1 + length of curve/2 ………......MC
- Chainage of
T2: Chainage
of IP + length of curve …………….EC
- Chainage of
next IP: Chainage
of T2 + IP distance – previous tangent length.
For the longitudinal section of the
road, elevation at every 15m chainage was taken and also at the beginning, mid
– point and end of curve points of the road alignment. If there is any specific
change in between, it was also recorded.
Elements
of L – section are:
·
Ground level
·
Formation level
·
Gradient of formation level
·
Volume of cut/fill
·
Soil type
·
Cross drainage
L – Section are plotted in graph with horizontal
1:1000 and vertical 1:100
4.7.6 CROSS – SECTION
Cross sections at different points are drawn
perpendicular to the longitudinal section of the road on either side of its
centerline in order to present the lateral outline of the ground. Cross
sections are also equally useful in determining the amount of cut and fill
required for the road construction. Cross sections were taken at 15 m intervals
along the centerline of the road and details were taken as possible as up to
15m left and right also at points where
Elements of
cross – section
·
Ground level
·
Formation level with road width
·
Retaining walls and drainage
·
Cambers provided
X – Section are plotted in graph with both vertical
and horizontal 1:100
4.5.7 PLAN VIEW OF PROPOSED ROAD
The plan view of proposed road is the actual path of
road designed.
Elements of plan view
·
Horizontal curve
·
Intersection points
·
Cross drainage
·
Any details
4.10 CONCLUSION
After the practice of this road
alignment survey, we are able to design roads at difficult terrain taking
factors like economy, convenience and its use into consideration. This survey
gave us apt concept of different road design practice and made us confidence
about practical design problems. We believe that such a work will be a lot of
help for us in understanding the actual situation while undertaking actual
design and construction work in the future.
0 comments:
Post a Comment