CHAPTER – 1 INTRODUCTION
1.1
Definition
Estimating is the
process of calculating the quantities and cost of various item required in
connection with work. It is necessary to estimate the amount of fund required
for the proposed work otherwise; it may so happen that the work has to be
stopped before its completion due to shortage of funds or of materials.
1.2
Estimated cost and Actual cost
Estimated cost is the
theoretical cost of the work/ probable cost of the work. Actual cost is the
expenditure, after completion of the work from account register of the
completed work.
Estimate is never the
actual cost of the work. Justify
An estimate is the
probable cost of construction work which is computed from the dimensions on the
drawings and the standing rates at the time of preparation of the estimate. The
accuracy of the estimate depends on the skill and experience of estimator.
Actual cost of construction can be known from the physical measurements of the
dimensions for various items of works at site and the actual rates of at such
items of works during execution off work. All expenses for all probabilities
can be known after completion of works as well as account. So, it can be
justified that whatever method may be adopted, in general all estimates are
approximate in nature and the difference between the estimated cost and actual
cost is vital issue. Although estimated cost is never the actual cost of work,
it should be close.
1.3
Purpose of estimating
The estimating is very
important for the developing country as they have taken fund as debt from
different agencies which charges high interest rate. The estimating gives
general idea about time and fund required. The main purposes of the estimating
are highlighted below:
·
Too give idea of the cost of the
work
·
To estimate various materials
required to completing a particular work
·
To estimate various categories
of labours required to completing a particular work.
·
To estimate various tools and
plants required to completing a particular work.
·
To justify the investment from
benefit/cost ratio
·
To estimate time of completion
of work
·
To invite the tenders and
prepare bills for payment
·
To estimate the existing
property for valuation.
·
To draw up the construction
schedule etc.
1.4
Principle of units and measurement
The units of measurement
mainly depend upon shape, size and nature of work.
1. Mass, voluminous and
thick works shall be taken in m3. (E/W, B/W)
2. Shallow, thin and
surface works shall be taken in m2
(DPC,
Shutters)
3. Long and thin walls
shall be taken in running unit (rm). (Skirting, Handrail)
4. Piece works, Job
works shall be taken in number (Tube light, wash basin)
1.5
Units of Measurement and Payment for various items of work
Item No.
|
Description
of work
|
Unit of
Measurement
|
Unit of
Payment
|
1.
|
Earthwork
|
||
1.1
|
E/W in excavation in
foundation
|
m3
|
Per % m3
|
1.2
|
E/W in filing
|
m3
|
Per % m3
|
1.3
|
Surface dressing
|
m2
|
Per m2
|
1.4
|
Surface excavation
|
m2
|
Per m2
|
2.
|
Brickwork
|
||
2.1
|
Brick on flat soling
|
m2
|
Per m2
|
2.2
|
B/W in foundation
|
m3
|
Per m3
|
2.3
|
B/W in superstructure
|
m3
|
Per m3
|
2.4
|
B/W in arches
|
m3
|
Per m3
|
2.5
|
B/W in Cornice
|
m
|
Per m
|
2.6
|
Half brick thick wall
|
m2
|
Per m2
|
3.
|
Concrete works
|
||
3.1
|
PCC in foundation
|
m3
|
Per m3
|
3.2
|
Lime concrete in foundation
|
m3
|
Per m3
|
3.3
|
PP for RCC walls
|
m3
|
Per m3
|
3.4
|
50mm thick PCC in floor
|
m2
|
Per m2
|
3.5
|
Formwork for RCC work
|
m2
|
Per m2
|
3.6
|
Steel Reinforcement
|
Kg or MT
|
Per kg or MT
|
4.
|
Wood work
|
||
4.1
|
Wood works for doors and
window frame
|
m3
|
Per m3
|
4.2
|
Doors and window shutters
|
m2
|
Per m2
|
4.3
|
Wood works for trusses
|
m3
|
Per m3
|
4.4
|
Wood works for rafters, wall
plate etc.
|
m3
|
Per m3
|
4.5
|
Wood work for false ceiling
|
m2
|
Per m2
|
4.6
|
Wooden partition
|
m2
|
Per m2
|
5.
|
Iron works
|
||
5.1
|
M.S grill
|
m2
|
Per m2
|
5.2
|
Tubular trusses and purlins
|
Quintal or kg
|
Per kg
|
6
|
Flooring works
|
||
6.1
|
Sand filling
|
m3
|
Per m3
|
6.2
|
Cement sand screed
|
m2
|
Per m2
|
6.3
|
Marble flooring
|
m2
|
Per m2
|
6.4
|
Flagstone flooring
|
m2
|
Per m2
|
7.
|
Roofing Work
|
||
7.1
|
C.G.I sheet roofing
|
m2
|
Per m2
|
7.2
|
Tile roofing
|
m2
|
Per m2
|
7.3
|
C.G.I sheet on gutter ridge
|
m
|
Per m
|
7.4
|
Tile on ridge
|
m
|
Per m
|
8.
|
Plaster and Pointing works
|
||
8.1
|
Pointing works
|
m2
|
Per m2
|
8.2
|
Plastering works
|
m2
|
Per m2
|
9.
|
Painting and Polishing works
|
||
9.1
|
Enamel Painting
|
m2
|
Per m2
|
9.2
|
Washable distemper
|
m2
|
Per m2
|
9.3
|
French Polishing
|
m2
|
Per m2
|
1.6
Data required for estimating
The requirements for
estimating are mentioned below:
1. Drawings:
The drawing is the basis
from which quantities of various items for a work are calculated, so fully
dimensioned drawings must be prepared showing plans, different sections and
other relevant details for the work.
2. Specification
i. General Specification:
In general specifications
the nature and class of work and the names of materials that could be used are
described. This forms a general idea for the project.
ii. Detailed specification:
Detailed specifications
describe every item of work in the estimate. This specifies the qualities, quantifies
and proportions of materials, workmanships, method of preparation and execution
for different items of works in a project. Thus, specification of a work serves
as a guide to the supervising staff of the contractor as well as to the owner
to execute the works to their satisfaction.
3. Rates
Quantities of different
items of works are estimated from the drawing and these are multiplied by the
rates. So, rates for different item of works are vital factor to determine the
estimated cost. Normally, the Engineering Departments provide with the current
schedule of rates per unit of work, materials, wages of labour transport etc.
In case when such rate is not found in the schedule, this is worked out by
analysis.
4. Updated mode of measurement
Updated modes of
measurement for standard deductions or additions are also necessary to
determine the correct quantities of works.
5. Standing circulars
Standard circulars for
taxes and insurance etc. are required to fix up rates of those items which are
not in the schedule of rate.
Reference
1. “Estimating, Costing, Specification and
Valuation in Civil Engineering” by M Chakraborti
2. “Estimating and Costing” by B.N. Dutta
0 comments:
Post a Comment