Translate

Wednesday, May 13, 2020

Estimating and Costing Chapter One Note


CHAPTER – 1 INTRODUCTION
1.1 Definition
Estimating is the process of calculating the quantities and cost of various item required in connection with work. It is necessary to estimate the amount of fund required for the proposed work otherwise; it may so happen that the work has to be stopped before its completion due to shortage of funds or of materials.

1.2 Estimated cost and Actual cost
Estimated cost is the theoretical cost of the work/ probable cost of the work. Actual cost is the expenditure, after completion of the work from account register of the completed work.
Estimate is never the actual cost of the work. Justify
An estimate is the probable cost of construction work which is computed from the dimensions on the drawings and the standing rates at the time of preparation of the estimate. The accuracy of the estimate depends on the skill and experience of estimator. Actual cost of construction can be known from the physical measurements of the dimensions for various items of works at site and the actual rates of at such items of works during execution off work. All expenses for all probabilities can be known after completion of works as well as account. So, it can be justified that whatever method may be adopted, in general all estimates are approximate in nature and the difference between the estimated cost and actual cost is vital issue. Although estimated cost is never the actual cost of work, it should be close.

1.3 Purpose of estimating
The estimating is very important for the developing country as they have taken fund as debt from different agencies which charges high interest rate. The estimating gives general idea about time and fund required. The main purposes of the estimating are highlighted below:
·         Too give idea of the cost of the work
·         To estimate various materials required to completing a particular work
·         To estimate various categories of labours required to completing a particular work.
·         To estimate various tools and plants required to completing a particular work.
·         To justify the investment from benefit/cost ratio
·         To estimate time of completion of work
·         To invite the tenders and prepare bills for payment
·         To estimate the existing property for valuation.
·         To draw up the construction schedule etc.

1.4 Principle of units and measurement
The units of measurement mainly depend upon shape, size and nature of work.
1. Mass, voluminous and thick works shall be taken in m3. (E/W, B/W)
2. Shallow, thin and surface works shall be taken in m2  (DPC, Shutters)
3. Long and thin walls shall be taken in running unit (rm). (Skirting, Handrail)
4. Piece works, Job works shall be taken in number (Tube light, wash basin)

1.5 Units of Measurement and Payment for various items of work

Item No.
Description of work
Unit of Measurement
Unit of Payment
1.
Earthwork


1.1
E/W in excavation in foundation
m3
Per % m3
1.2
E/W in filing
m3
Per % m3
1.3
Surface dressing
m2
Per m2
1.4
Surface excavation
m2
Per m2




2.
Brickwork


2.1
Brick on flat soling
m2
Per m2
2.2
B/W in foundation
m3
Per m3
2.3
B/W in superstructure
m3
Per m3
2.4
B/W in arches
m3
Per m3
2.5
B/W in Cornice
m
Per m
2.6
Half brick thick wall
m2
Per m2




3.
Concrete works


3.1
PCC in foundation
m3
Per m3
3.2
Lime concrete in foundation
m3
Per m3
3.3
PP for RCC walls
m3
Per m3
3.4
50mm thick PCC in floor
m2
Per m2
3.5
Formwork for RCC work
m2
Per m2
3.6
Steel Reinforcement
Kg or MT
Per kg or MT




4.
Wood work


4.1
Wood works for doors and window frame
m3
Per m3
4.2
Doors and window shutters
m2
Per m2
4.3
Wood works for trusses
m3
Per m3
4.4
Wood works for rafters, wall plate etc.
m3
Per m3
4.5
Wood work for false ceiling
m2
Per m2
4.6
Wooden partition
m2
Per m2




5.
Iron works


5.1
M.S grill
m2
Per m2
5.2
Tubular trusses and purlins
Quintal or kg
Per kg




6
Flooring works


6.1
Sand filling
m3
Per m3
6.2
Cement sand screed
m2
Per m2
6.3
Marble flooring
m2
Per m2
6.4
Flagstone flooring
m2
Per m2




7.
Roofing Work


7.1
C.G.I sheet roofing
m2
Per m2
7.2
Tile roofing
m2
Per m2
7.3
C.G.I sheet on gutter ridge
m
Per m
7.4
Tile on ridge
m
Per m




8.
Plaster and Pointing works


8.1
Pointing works
m2
Per m2
8.2
Plastering works
m2
Per m2




9.
Painting and Polishing works


9.1
Enamel Painting
m2
Per m2
9.2
Washable distemper
m2
Per m2
9.3
French Polishing
m2
Per m2

1.6 Data required for estimating

The requirements for estimating are mentioned below:
1.       Drawings:
The drawing is the basis from which quantities of various items for a work are calculated, so fully dimensioned drawings must be prepared showing plans, different sections and other relevant details for the work.

2.       Specification
i. General Specification:
In general specifications the nature and class of work and the names of materials that could be used are described. This forms a general idea for the project.
ii. Detailed specification:
Detailed specifications describe every item of work in the estimate. This specifies the qualities, quantifies and proportions of materials, workmanships, method of preparation and execution for different items of works in a project. Thus, specification of a work serves as a guide to the supervising staff of the contractor as well as to the owner to execute the works to their satisfaction.

3.       Rates
Quantities of different items of works are estimated from the drawing and these are multiplied by the rates. So, rates for different item of works are vital factor to determine the estimated cost. Normally, the Engineering Departments provide with the current schedule of rates per unit of work, materials, wages of labour transport etc. In case when such rate is not found in the schedule, this is worked out by analysis.  

4.       Updated mode of measurement
Updated modes of measurement for standard deductions or additions are also necessary to determine the correct quantities of works.

5.       Standing circulars
Standard circulars for taxes and insurance etc. are required to fix up rates of those items which are not in the schedule of rate.
Reference
1. “Estimating, Costing, Specification and Valuation in Civil Engineering” by M Chakraborti
2. “Estimating and Costing” by B.N. Dutta

Share:

0 comments:

Post a Comment

Recent Posts

Contact us: Feel free to contact us

Name

Email *

Message *

About

This just a demo text widget, you can use it to create an about text, for example.
Powered by Blogger.

Search This Blog

Logo

Pages